Planned power outage on campus
Posted on 30 November 2022
On 6 and 7 December, there will be a planned power outage for approximately 4-6 hours in Market Square and Wentworth College Sub-Stations.
As part of our ongoing statutory safety compliance we are required to carry out some essential testing to our electrical systems. To operate with continued resilience and reliability this safety compliance testing must take place. Unfortunately the work will cause some disruption to the power supply in some areas on campus.
Between specific hours there will be no electricity, heating and hot water available. This includes kitchens, bathrooms and other shared areas. Cold water supplies will remain unaffected meaning toilets/cold taps etc will work as normal.
Wentworth College Sub-Station - Tuesday 6 December, from 9am
A full power outage will take place on Tuesday 6 December from 09:00 for approximately 4-6 hours. The fire alarm will be fully operational throughout this work.
The following areas will be affected:
- Wentworth College - Block A
- Wentworth College - Block B
- Wentworth College - Block C
- Wentworth College - Block D
- Wentworth Nucleus Including Kitchens and Drama Studio's
- New Environment Building
Market Square Sub-Station - Wednesday 7 December, from 9am
A full power outage will take place on Wednesday 7 December from 09:00 for approximately 4-6 hours. The fire alarm will be fully operational throughout this work.
The following areas will be affected:
- Drama Barn
- Music Research Department and Jack Lyons
- The Warren (Vanbrugh Provost House)
- Market Square Development
- Sally Baldwin A-D Blocks
The IT network will also be affected for the following buildings below:
- Jack Lyons Concert Hall
- Sally Baldwin blocks